PropertyTeton County

6635 W HIGHWAY 22, WILSON, WY

$1.2M across 2 construction permits, all closed. Lead: With The Grain LLC.

📁 2 permits 📐 1.04 acres
Assessed value & lot dataTeton County Assessor, 2025 Tax Roll
Actual value (market)
$446,653
Assessed (taxable)
$42,432
Annual tax
$2,410
Mill levy
56.7990
Owner of record · legal description · value breakdown
Tax-Roll owner
HUCK & CHUCK, LLC
PO BOX 171, SWAN VALLEY, ID 83449-0171
Tax district
District 0100
Legal description
Sub T-131C · Filing 1 · Lot 3
Value breakdown (2 components)
  • Other Structure $1,967 actual · $187 assessed
  • Vacant Land $444,686 actual · $42,245 assessed
Owner — out-of-state (ID)
Huck & Chuck LLC
PO Box 171, Swan Valley, ID 83349
Architects of record
Caleb Spahemberger
📞 2087260020
Caleb Spangenberger
📞 208-726-0020
Applicant
Kurt Stout
📞 3077390500
🛠 Project team — 1 company
Regulatory flags
Floodzone: X Construction: VB

Permits at this property

Active since 2026

Single-family new construction

$1,200,000 combined
👷 Lead: With The Grain LLC 🪪 CL-24-0128
BDR2022-0201 ↗ Construction Single-family new construction Closed $900K 5/20/2026

$900K new single-family build at 6635 W Highway 22, Wilson — 2,490 sqft, 3 bed/2 bath, Type VB construction with hydronic + mini-split heat, metal roof and wood siding; out-of-state LLC owner (Swan Valley, ID), applicant Kurt Stout (307-739-0500), architect Caleb Spahemberger (208-726-0020).

📎 1 doc 📜 7 cond.· 5 awaiting
📎 Documents (1)
📜 Conditions (7) 5 awaiting
  • Awaiting Verification Structures within the Wildland-Urban Interface must show compliance with the Fire Marshal’s requirements by means of details and/or notes on the submitted plans
  • Awaiting Verification Stamped and approved job site plans shall remain on site throughout the project.
  • Awaiting Verification A Certificate of Placement prepared by a Wyoming licensed Professional Land Surveyor is required for each structure. The location of the structure foundation shall be prepared by the Professional Land Surveyor and submitted to the Teton County Planning & Building Services Department prior to the foundation walls being poured. A foundation wall inspection cannot be scheduled until receipt of certificate showing the location of the foundation matches the approved plans and is approved by the Planning Department.
  • Awaiting Verification All exterior lighting shall comply with the Exterior Lighting Standards of Section 5.3.1, Land Development Regulations. Lighting shall be installed per the approved plans. Should the exterior lighting change in any way, the applicant shall submit revisions including spec sheets to the Planning Department for review and approval, prior to issuance of a Certificate of Occupancy or prior to final inspection of the permitted work. Changes to lighting that require review include fixture design, location of fixtures, the number of fixtures, and lumen amount. Approved for 4 shielded sconces and 2 steps.
  • Approved bear resistant trash containers are required per Section 5.1.3, Wild Animal Feeding, Land Development Regulations. At construction sites, all trash recepticles for trash that includes food, food wrappers, or other bear attractants shall be bear-resistant. Containers shall be kept closed and latched at all times. Non-bear-resistant dumpsters or trailers may only be used to store construction trash that does not contain bear-attractants.
  • Any changes to the design, including the structure or site development, require a plan revision. Please submit to the Building DIvision a Letter of Transmittal for Building Permit Revision with appropriate revised drawings. Fees will be assessed for additional square footages, plumbing, mechanical or electrical work, including additional plan review fees. Revisions to Grading and Septic may also be applicable.
  • Awaiting Verification Conditions of ADJ2023-0003 shall apply
BDR2022-0202 ↗ Construction Single-family new construction Closed $300K 5/20/2026

$300K new single-family build at 6635 W Hwy 22, Wilson — 991 sqft, 1BR/1BA with hydronic + forced-air heat, metal roof, and wood siding; Idaho-based LLC owner (Swan Valley), applicant Kurt Stout, architect Caleb Spangenberger (208-726-0020).

📎 3 docs 📜 10 cond.· 9 awaiting
📎 Documents (3)
📜 Conditions (10) 9 awaiting
  • Awaiting Verification Structures within the Wildland-Urban Interface must show compliance with the Fire Marshal’s requirements by means of details and/or notes on the submitted plans
  • Awaiting Verification Stamped and approved job site plans shall remain on site throughout the project.
  • Awaiting Verification A Certificate of Placement prepared by a Wyoming licensed Professional Land Surveyor is required for each structure. The location of the structure foundation shall be prepared by the Professional Land Surveyor and submitted to the Teton County Planning & Building Services Department prior to the foundation walls being poured. A foundation wall inspection cannot be scheduled until receipt of certificate showing the location of the foundation matches the approved plans and is approved by the Planning Department.
  • Awaiting Verification All exterior lighting shall comply with the Exterior Lighting Standards of Section 5.3.1, Land Development Regulations. Lighting shall be installed per the approved plans. Should the exterior lighting change in any way, the applicant shall submit revisions including spec sheets to the Planning Department for review and approval, prior to issuance of a Certificate of Occupancy or prior to final inspection of the permitted work. Changes to lighting that require review include fixture design, location of fixtures, the number of fixtures, and lumen amount. Approved for 5 shielded sconces and 1 step.
  • Approved bear resistant trash containers are required per Section 5.1.3, Wild Animal Feeding, Land Development Regulations. At construction sites, all trash recepticles for trash that includes food, food wrappers, or other bear attractants shall be bear-resistant. Containers shall be kept closed and latched at all times. Non-bear-resistant dumpsters or trailers may only be used to store construction trash that does not contain bear-attractants.
  • Awaiting Verification Any changes to the design, including the structure or site development, require a plan revision. Please submit to the Building DIvision a Letter of Transmittal for Building Permit Revision with appropriate revised drawings. Fees will be assessed for additional square footages, plumbing, mechanical or electrical work, including additional plan review fees. Revisions to Grading and Septic may also be applicable.
  • Awaiting Verification The occupancy of this accessory residential unit is restricted to employees working within Teton County, family members and guests.
  • Awaiting Verification All possessions belonging to the occupants of an accessory unit, such as recreational, secondary or inoperative vehicles, boats, motorcycles, lumber and other construction materials not associated with an on-going construction project on the site, or other similar items contributing to an untidy appearance, shall be stored within an enclosed structure, such as a garage or barn. Only vehicles used for daily travel may be stored outside.
  • Awaiting Verification If the accessory residential unit unit is to be rented, the tenants shall be provided with a minimum 90-day lease.
  • Awaiting Verification Access to attic space shall be blocked off from having direct access from within the ARU.
🕒 Recent activity — 10 events on record
Show 4 more routine events
  • New Residential New Construction (Includes Remodel and Addition) at 6635 W HIGHWAY 22, WILSON, WY yesterday
  • New Residential New Construction (Includes Remodel and Addition) at 6635 W HIGHWAY 22, WILSON, WY yesterday
  • New Residential New Construction (Includes Remodel and Addition) at 6635 W HIGHWAY 22, WILSON, WY yesterday
  • New Residential New Construction (Includes Remodel and Addition) at 6635 W HIGHWAY 22, WILSON, WY yesterday